Construction law lawyer in Paris: five regimes, one timeline

Building, buying off-plan or running a project involves large sums and an interlocking set of guarantees. The firm brings together here its construction law work, from the contract to the repair of defects. It acts for clients and before courts throughout France.

Call

Our construction law services

Each stage has its own regime and deadlines. Choose the topic that matches your situation.

Five regimes, one preliminary question

Construction law is rarely difficult for technical reasons. The difficulty lies in a preliminary question, usually asked too late: which regime does your project fall under. The contract signed, the status of the parties and the presence or absence of a formal handover determine everything else, starting with the time you have to act.

Five regimes, one preliminary question
Your projectApplicable regimeWhat it changes
You are having a house built and entrust the plans and the works to a single professionalIndividual house construction contractFixed price, capped payment schedule, compulsory completion guarantee, ten-day withdrawal period
You are buying a new home before it is builtOff-plan saleRegulated staged payments, financial completion guarantee, 5 % held in escrow at delivery
You entrust works to one or more contractors, with no single builderPrivate works contractFreedom of contract, but article 1793 on extra works, retention money, subcontracting rules
A defect appears after handoverStatutory construction guaranteesDefects liability one year, working order two years, decennial ten years
A serious defect compromises the worksDecennial guarantee and damage insuranceStrict liability, pre-funding by the insurer without waiting for a trial

The timeline of a project, from contract to expiry of the guarantees

This timeline applies to most projects. The durations depend on the project itself.

The timeline of a project, from contract to expiry of the guarantees
StageWhat is at stakeMarker
Before signatureChoice and classification of the contract, checking the compulsory guaranteesNo statutory deadline. In a CCMI the contract itself sets the long-stop date for the conditions precedent, article L231-4
SignatureStart of the withdrawal period where one existsTen days for a CCMI and for a non-professional buyer
WorksPayment requests, extra works, delays, possible abandonmentTwo months to obtain the building permit for a house, article R423-23, then nine to twelve months of works on average
HandoverThe central act: it starts every guarantee and clears visible defects not recordedDay zero for the guarantees
The following yearDefects-liability guarantee, lifting of reservations, retention money1 year
Two yearsWorking-order guarantee on separable equipment2 years
Ten yearsDecennial guarantee and intermediate defects10 years

One point matters more than the rest: handover governs everything. Without it, no statutory guarantee runs. With it, every period starts on the same day, and none of them reopens.

Which defect falls under which guarantee

This is the question that decides the outcome, and it arises before the question of who is liable.

Which defect falls under which guarantee
Nature of the defectGuarantee availableDuration
Reservation recorded at handover, or defect appearing within the yearDefects liability, article 1792-61 year from handover
Faulty separable equipment: roller shutter, water heater, entryphoneWorking order, article 1792-32 years from handover
Damage to the soundness of the works, or works made unfit for their purposeDecennial, article 179210 years from handover
Less serious defect, but resulting from the builder's faultContractual liability, article 1792-4-310 years from handover
Equipment installed on existing works: heat pump, boiler, solar panelsOrdinary contractual liability, unless the equipment is itself a workAs per the contract

That last line is recent and it changes many cases. Since a reversal of case law on 21 March 2024, an item of equipment installed on existing works falls under the decennial guarantee only if it constitutes a work in its own right. A heat pump fitted to an older house therefore no longer benefits, in principle, from the decennial regime.

What the firm brings at each stage

What the firm brings at each stage
When we actWhat we doWhat you receive
Before signingClassification of the contract, review, checking the compulsory guaranteesA risk note and the list of amendments to obtain
During the worksChecking payment requests, formal notices, handling extra worksUseful correspondence and a position that holds
At handoverPreparing and drafting the reservations, advice on being assistedA usable handover report and preserved deadlines
After a defect appearsClassification, claim notification, interim application for an expertThe right guarantee called, within the right time
In litigationQuantification, proceedings against the builders and their insurersA documented compensation claim

Our billing arrangements are set out on our fees page.

Choose your topic

See all our real estate law services.

Maître Léa Scemama

Written by Maître Léa Scemama, admitted to the Paris Bar, Miraï Avocats. This page states the law applicable at its update date. It is general in nature and does not constitute advice tailored to a particular situation.