French construction warranties: key dates and late-delivery penalties

Building or buying new in France gives you three statutory warranties: one year for completion defects, at least two years for equipment and ten years for serious defects. All three run from formal acceptance of the works: acceptance on 15 June 2026 opens a one-year warranty until 15 June 2027.

Enter the acceptance date: the tool works out each expiry date and, if the work was late, the penalties. The firm handles construction defects throughout France, in English.

Updated on , by Maître Léa Scemama

Work out when your warranties expire

The date of the signed acceptance report, not the end of the building work or the handover of keys.

Late-delivery penalties (optional)

Fill in this section if the building was handed over late.

Type of contract

In a house-building contract, it replaces the legal minimum if it is higher.

Leave blank if the house has not been handed over yet: the tool counts up to today.

Indicative result

Enter the acceptance date to see the expiry dates.

Dates and amounts worked out from your entries. The acceptance date, any reservations and the terms of the contract can change them. Nothing is sent anywhere: the calculation runs in your browser.

Provisions applied: art. 1792-3, 1792-4-1, 1792-6 of the French Civil Code, art. R. 231-14 of the Construction and Housing Code

How long French construction warranties last

Length, starting point and scope of the three French construction warranties
WarrantyLengthWhat it coversProvision
Completion warranty1 year from acceptanceAll defects reported, by reservations at acceptance or by written notice afterwardsCivil Code, art. 1792-6
Equipment warrantyAt least 2 years from acceptanceEquipment that is not inseparable from the buildingCivil Code, art. 1792-3
Ten-year structural warranty10 years from acceptanceDamage that undermines the soundness of the building or makes it unfit for its purposeCivil Code, art. 1792 and 1792-4-1

Formal acceptance: the date everything depends on

Acceptance is the act by which the owner declares that it accepts the works, with or without reservations. It takes place at the request of either party, by agreement or failing that through the courts, and always in the presence of both parties (article 1792-6 of the French Civil Code).

The acceptance date starts all three warranties. It must therefore be certain: a dated report signed by both parties is the best evidence.

  • Reservations. Record every visible defect in the acceptance report. It is through these reservations that the one-year warranty covers defects visible on the day.
  • No written report. Where there was no written acceptance, the date can be disputed, and with it the end of each warranty. Have that point settled before a deadline is at stake.

The one-year completion warranty: report everything

For one year from acceptance, the contractor must repair every defect the owner reports, either through reservations in the acceptance report or, for defects that appear later, by written notice (article 1792-6 of the Civil Code).

Repair times are agreed between the parties. Failing agreement, or if the contractor does not do the work in time, the owner can, after formal notice has gone unanswered, have the work done at the defaulting contractor’s cost and risk.

The warranty does not cover work needed because of normal wear and tear or use. One year passes quickly: send a dated written notice you can prove well before the date the tool shows.

The two-year equipment warranty

Items of equipment that are not inseparable from the building within the meaning of article 1792-2 carry a warranty of proper working for at least two years from acceptance (article 1792-3 of the Civil Code).

An item of equipment is inseparable from the roads and services, foundations, frame, walls or roof of the building when it cannot be removed, dismantled or replaced without damaging or removing material from them. Damage to its soundness then falls under the ten-year warranty (article 1792-2).

The ten-year warranty for serious defects

Every builder is strictly liable to the owner or buyer for damage, even from a defect in the ground, that undermines the soundness of the building or, affecting one of its structural parts or items of equipment, makes it unfit for its purpose. The builder escapes liability only by proving an external cause (article 1792 of the Civil Code).

The builder is released from this liability ten years after acceptance of the works (article 1792-4-1).

Strict liability means the owner does not have to prove fault. It must show the damage, its seriousness and its link with the works. The defects covered are detailed on our page on the ten-year warranty.

Late-delivery penalties: the legal minimum for a new house

In a French contract to build a house that includes the design, penalties for late delivery cannot be set below 1/3,000 of the agreed price per day of delay (article R. 231-14 of the French Construction and Housing Code).

Worked example of late-delivery penalties

Minimum penalties for a €240,000 price and 45 days of delay
ItemValue
Agreed price€240,000
Minimum daily penalty240,000 ÷ 3,000 = €80
Delay45 days
Penalties due€3,600

These figures are a worked example. The contract can set a higher amount, never a lower one.

For other contracts, including off-plan purchases and works contracts, penalties depend on the contract terms. The tool lets you enter the daily amount the contract sets. See also our page on the house-building contract.

Mistakes that cost owners their warranty

  • Counting from moving in or the key handover. The periods run from acceptance.
  • Reporting a defect by phone. The one-year warranty requires reservations in the report or written notice.
  • Waiting until the last week. When the expiry date is close, a letter may not be enough to protect your rights: court action may be needed before the date.
  • Mixing up the warranties. A broken roller shutter and a crack right through a wall do not fall under the same period.

Building defects insurance is not covered by this tool: its notice and reply periods are set by the French Insurance Code.

Frequently asked questions

Does the ten-year warranty run from the end of the building work?

It runs from formal acceptance of the works, which can come after the work is physically finished.

Is a defect that appears after one year still covered?

Yes if it falls under the equipment warranty, for at least two years, or the ten-year warranty. It depends on its nature and seriousness.

Are late-delivery penalties automatic?

They are due under the contract. In a house-building contract that includes the design, they cannot be less than 1/3,000 of the price per day of delay. The agreed and actual delivery dates still have to be established.

What about acceptance on 29 February?

The following years have no 29 February: the tool then uses 28 February, the more cautious reading.

Contact

A warranty about to expire, or late delivery?

The firm serves formal notice on the builder, starts the expert assessment and brings proceedings before the deadline, throughout France and in English.

References

Maître Léa Scemama

Written by Maître Léa Scemama, member of the Paris Bar, Miraï Avocats. This page sets out the law as it stood on the date it was last updated. It is general information, not advice on your particular situation.